The expansion of artificial intelligence and the growth of infrastructure continue to drive the data center business. However, the sector is beginning to face a challenge that goes beyond the availability of technology or the demand for capacity: ensuring that projects come to fruition within the planned deadlines.
This is one of the main conclusions of the latest report from Bank of America Securities, which, under the title Data center infrastructure: demand isn’t the problem, execution is, analyzes the market situation based on meetings held with representatives of 14 companies during the SuperCompute26 (SC26) conference, held in Chicago.
The financial institution’s diagnosis is clear: the demand signals continue to be extraordinarily positive. More demanding financing conditions and more rigorous criteria for approving projects have not yet slowed orders or the growth of manufacturers’ commercial portfolios. However, difficulties in executing investments and possible excess supplies are beginning to become the main concerns for 2027.
Projects that are not progressing at the planned pace
One of the aspects that most caught the attention of analysts was the number of projects that accumulate significant delays. Several managers present at SC26 acknowledged that they are aware of initiatives that are progressing far behind their initial schedules. In this sense, the report includes a particularly significant statement from one of the commercial representatives consulted: “Neoclouds are not complying.”
The difficulties are not new. A JLL survey cited by Bank of America indicates that 57% of data center projects suffered delays of more than three months during 2025. Added to this is a report from S&P Global from October 2026, according to which 146 US projects were delayed, mainly due to opposition from local communities.
The impact of these breaches can be considerable. The contracts contemplate increasing penalties for the developers, which can begin with compensation in the form of credits on rents and go, in certain cases, to the termination of the agreements by the clients. Analysts also see an increase in cancellations of third-party projects and the withdrawal of preliminary leasing commitments, such as non-binding rental intent agreements, as possible.
Prefabricated construction gains prominence
In this scenario, delays are favoring the demand for prefabricated and modular solutions. The possibility of moving part of the work off-site and reducing installation times is becoming a competitive advantage for infrastructure manufacturers.
Bank of America identifies opportunities for companies such as Vertiv, Eaton — which strengthened its position with the $1.4 billion acquisition of Fibrebond in April 2025 — Forgent and Accelevation. The report also includes the expectations of a private manufacturer of containerized structures, whose CEO plans to close 2026 with an order book equivalent to more than a year of activity.
Electrification and cooling are also becoming increasingly important. Increasing energy density of racks and the need to power increasingly demanding computing systems are driving the transition toward new electrical architectures and advanced thermal solutions.
The risk of over-ordering
The other major concern emerging from conversations with manufacturers is the possibility that some customers are ordering more than their actual needs. Although none of the companies consulted had recorded cancellations or reductions of firm orders by original equipment manufacturers (OEM), several component suppliers recognized that this scenario constitutes one of their main risks.
The concern responds to the fact that some manufacturers would be communicating especially ambitious production plans to encourage their suppliers to expand capacity. The question is whether all this growth can materialize. One of the suppliers consulted summed it up with a question: “All of our cooling distribution unit (CDU) customers are growing more than 100% in 2026 and plan to do so in 2027 as well. Can they all be right?”
Despite these reservations, the general sentiment remains positive. A manager of a thermal equipment company assured that he does not perceive doubts among customers, price problems or cancellations. Even if a particular project stalls, computing equipment could end up being installed in another location, keeping demand for infrastructure alive.
More voltage and new cooling demands
The report also points to technological changes that will mark the evolution of the sector. One of them is the transition to 800 volt direct current systems (800 VDC), whose first scale implementations could occur during the second half of 2027. Their adoption will be conditioned by the need to establish clear safety standards and train the professionals in charge of their installation and operation. The increase in the energy density of the racks will, however, be one of the main drivers of this evolution.
Power electronics are also raising cooling demands. The solid-state transformers observed during SC26 incorporated liquid cooling, as did some power systems. The reason is simple: overheating can cause failure of these components, which is why thermal management becomes increasingly relevant.
The ability to convert investment announcements into operational facilities will be as important as demand itself
Finally, standardization gains ground with two references: the Open Compute Project (OCP) certification, which seeks to facilitate interoperability between manufacturers and reduce dependence on a single supplier, and Nvidia DSX Ready, which accredits the compatibility of the equipment with its reference architecture. Both certifications were widely represented at the conference.
In short, the data center infrastructure market maintains solid growth prospects, but is entering a phase in which the ability to convert investment announcements into operational facilities will be as important as demand itself. The question is no longer just how many data centers will be built, but how many can be completed on time and with what actual supply capacity.